PROJECT
Project Name   Beanibazar to Kailashtila Gas Transmission Pipeline Project
Project Type   Completed
Objective   To Evacuate gas and condensate from Beanibazar gas field to national grid.
Salient Feature   Length 18 km, dia 20 inch. Linepipe specification API 5L 60X LSAW. Thickness ----, Coating Hot applied Coal Tar Enamel and CC. Valve station 2 nos and scraper station 2 nos. Capacity 250 mmcfd(MAOP 1050 psig)



Others   Starting date june 1997, completion date September 2001. Approved Total cost Tk 29.15 crore(foreign:--, Local, 29.15). Actual cost Tk 27.15 crore(foreign:--, Local, 27.15
Contact Information  GM Planning
Download File