Construction of Gas Pipeline and KGDCL Gas Distribution Network Upgradation Project for Mirsarai Economic Zone

Project Director: Md. Abdul Momen
Project Name: Mirsarai Economic Zone Project
E-Mail: gtcl.mez@gmail.com
Cell No.:

 

Name of the Project: Construction of Gas Pipeline and KGDCL Gas Distribution Network Upgradation Project for Mirsarai Economic Zone

Implementation Period: June 2018 to December 2019

Project Cost: Total Rs. 39,72.00 lakhs (GTCL share Rs. 24,60.00 lakhs)

Job Description of GTCL Part:

  • Installation of a CGS with a capacity of 200 MMSCFD and two HP-DRS with a capacity of 50 MMSCFD within the Mirsarai Economic Zone.
  • Hot-tapping of 16 ”diameter with GTCL’s 24” diameter BKB-Chittagong gas transmission pipeline at Baratakia of Mirsarai
  • Construction of 16” diameter 17 km gas transmission pipelines from Baratakia of Mirsarai to Mirsarai Economic Zone
  • Construction of 16” diameter 25 km gas transmission pipelines from Anwara CGS to CUFF-Kafco and from Anwara CGS to Shikalbaha Pig Receiving Station.

 

2020-08-31T11:39:44+06:00 August 31st, 2020|