Construction of Transmission Pipeline along Padma Bridge

/Construction of Transmission Pipeline along Padma Bridge

Construction of Transmission Pipeline along Padma Bridge

As integral part of the Padma Bridge, the DPP for the Bridge includes construction of 30-inch 6.15-km gas transmission pipeline at a cost of Tk. 25,380.00 Lac under GoB funding. The Padma Multipurpose Bridge Authority has issued to the Company the draft Gas Pipeline Design Drawing (Version-C) & Structural Design Drawing (Version-2). The Company after examination of the Design/Drawing, the same has been returned to the Bangladesh Bridge Authority with comments. Bangladesh Bridge Authority, after finalization of the Design/ Drawing will construct the pipeline by their engaged contractor.

2019-02-25T09:24:48+06:00 January 15th, 2018|